Current
Development Status
PUDA has already issued
a completion certificate for construction of the mandatory colony infrastructure as per set standards. In addition
to mandatory development, a number of additional facilities have also been provided.
Several houses
have already been built and inhabited. Few more houses are under
construction, making this colony a highly sought after address.
Click
here to view pictures of how nicely the colony is turning out.
Current Development
Status:
| Major
Development Tasks |
Status
|
| Demarcation
of site and plots |
Completed
|
| Shifting
of high tension wires over plots |
Completed
|
| Earthwork
for access roads |
Completed
|
| Outer
Boundary Wall, Gates and Fencing |
Completed
|
| Trenches
for underground wiring |
Completed |
| Laying
of sewarage lines |
Completed
|
| Installation
of sewarage treatment plant |
Completed
|
| Construction
of Concrete Roads |
Completed
|
| Streetlighting |
Completed
|
| Storm
water drainage |
Completed |
| Laying
of footpaths and pavements |
Completed
|
| Electricity
supply and meter room |
Completed
|
| Construction
of Gaurd house & fountains |
Completed
|
| Construction
of Country Club building |
Completed |
| Landscaping
and beautification |
Ongoing
|
|